At 20:24 04/08/99 -0700, Ron Fial wrote: >efficient than AC 3-phase transmission, but the cost of the AC/DC conversion >only makes the DC transmission have better economics if the line is over 500 >km over land, or 20-50 km under the sea, or 40 km if all wires are >underground. Here are some interesting facts about this stuff. I don't >know why it only takes 20 km underground for DC to beat out AC. Maybe its >only one insulated wire required, so only one narrow trench? Any other >guesses? for underground and even more so for submarine cables the capacitive transmission losses may be higher, maybe. ge